Snow loads for steel buildings, explained without the jargon
2026-08-17 · 6 MIN READ · #snow load #engineering #codeGround snow load is the number your county publishes. It is not the number your roof is designed to. Here's how one becomes the other, and why drift usually decides the price.
Ground snow load vs. roof snow load
Ground snow load (Pg) comes from a code map — 20 psf in Columbus, 25 in Cleveland, 30 in Pittsburgh. Your engineer converts it to a flat-roof load using exposure, thermal, and importance factors, which usually lands somewhere between 70% and 100% of Pg.
Drift is where the money goes
Snow does not sit evenly. It piles against parapets, against taller adjacent structures, and — most commonly on the buildings we quote — against the wall where a lean-to meets the main building. Drift loads routinely run two to three times the flat-roof load in that strip, and they govern the framing there.
Practical decisions this affects
- Roof pitch: steeper roofs shed more, which can reduce the design load slightly, but they add panel area and cost.
- Lean-to placement: putting a lean-to on the leeward side changes the drift case, sometimes dramatically.
- Unheated buildings: a cold building carries a higher thermal factor than a heated one, so an unheated shop is designed for more snow than a heated one.
- Openings near drift zones: a big door under a drift strip may need a heavier header than the same door elsewhere.
If you don't know your snow load
That is completely normal and it does not slow your quote down. Give us the project ZIP and we pull the ASCE 7 value and any local amendment during estimating. It gets flagged on your project record as needing verification until an engineer confirms it.
Common follow-up questions
Who determines the snow load for my building?
The authority having jurisdiction — usually your county or city building department — sets the design ground snow load. The licensed engineer sealing your drawings applies the code conversions to that value.
Can I upgrade the snow load later?
Not practically. Frame members are sized for the design load at fabrication. If you expect to add a lean-to or solar later, tell your estimator now so the load allowance is designed in.
Snow, wind, permit review and freight change these numbers city by city. We quote and erect steel buildings in all 50 states — open your market for local loads, permitting and pricing:
- Steel buildings in Mobile, AL →
- Steel buildings in Mesa, AZ →
- Steel buildings in Colorado Springs, CO →
- Steel buildings in Stamford, CT →
- Steel buildings in Orlando, FL →
- Steel buildings in Honolulu, HI →
- Steel buildings in Boise, ID →
- Steel buildings in Springfield, IL →
Statewide guides: